|
1959 |
The Shine Pit opened as a temporary source
of materials for construction of the Hood
Canal
Bridge. |
|
1979 |
Fred Hill Material leased the Shine Pit
and began mining operations |
|
1994 |
DNR granted FHM their first expansion of
the Shine Pit |
|
1999 –2000 |
FHM began design and development of the
Pit to Pier proposal |
|
1999 |
FHM requested expansion of the Shine Pit
Mining Permit to the 156 acre Wahl Lake
site plus 9
acres for a mile long conveyor belt. This
is the first concrete step by FHM to piece
meal the Pit
to Pier project. (In July of 2002 DNR and
Jefferson County ruled the request was not
an
expansion but rather a new mine requiring
a new permit.) |
|
10-9-00 |
Ace Paving Asphalt Batch Plant permit was
issued |
|
10-23-00 |
DNR granted an expansion of approximately
23 acres at the Shine Pit increasing the
size of
the mine to 144acres |
|
4-24-01 |
FHM attorney Jim Tracy made an offer
through a real estate agent on the Groves
Way
property that ultimately was designated as
the site for the 1000 foot industrial
pier. |
|
5-2-01 |
Betsy Peabody, President of the Puget
Sound Restoration Fund, Tom Hujar, FHM
political
consultant and
Dan Baskins, FHM Pit to Pier project
manager, briefed Governor Locke’s
staff, WDFW,DOE, and DNR on
the Pit to Pier Project. They presented
it as a
beach restoration project.
|
|
8-6-01 |
FHM attorney Jim Tracy purchased the
Groves Way property, intended as the site
of the
industrial pier,
in his name for $270,000.
|
|
10-24-01 |
The first formal meeting is held between
FHM and Jefferson County DCD regarding
the
Pit to Pier Project. (It should
be noted this was prior to a
pre-application filing or
payment of
appropriate fees in violation of DCD
policy.)
|
|
1-16-02 |
A pre-application meeting was held between
FHM, the Corps of Engineers Seattle
Division,
state
and federal agencies.
|
|
2-8-02 |
FHM attorney Jim Tracy sold the Groves Way
“pier” property to Hood Canal Sand and
Gravel,
LLC (Actually FHM) for $209,840. (A
$60,160 loss??)
|
|
2-20-02 |
An “official” pre-application meeting
regarding the Pit to Pier Project was held
between FHM,
DCD, and other
county departments. Based on meeting notes
a Mineral Lands Resource
Overlay (MRLO) of
24,000 acres
was discussed.
|
|
3-1-02 |
Another meeting occurred between FHM and
Jefferson County regarding the Pit to Pier
Project. This time a
MRLO of 20,000 to 40,000 acres was
discussed.
|
|
3-20-02 |
A meeting was held with Al Scalf, Director
of DCD and Pit to Pier Project Manager
Dan Baskins. Meeting notes
reflect a discussion about a series of
future Shine Pit expansions
based upon the
capacity of the Pit to Pier
Project. Baskins requested a significant
current
expansion with a series of future
expansions as well as
additional MRLO’s in 2003, 2004 and
2005.
(this appears to be an attempt to piece
meal the Pit to Pier Project
through a series of
expansions of the
existing Shine Pit operation and future
consecutive MRLO’s)
|
|
4-9-02 |
Reporter Christopher Dunagan of the
Bremerton Sun broke the news story of the
proposed
Pit to Pier Project and made it public for the first time. The
article stated that FHM has been
working
on the project for two years.
|
|
4-17-02 |
FHM hosted a quickly pieced together
community meeting to inform residents of
the benefits
of the Pit to Pier
Project. Project Manager Dan Baskins
falsely advises the audience that
the
Governor’s Office, and others support
the project.
|
|
4-30-02 |
FHM applied for a Comprehensive Plan
Amendment to designate an additional 6,240
acres
of Pope commercial
forest as a Mineral Resource Land Overlay
(MRLO). DCD meeting notes
indicated plans
for future MRLO requests
ultimately totaling 20,000 to 40,000
acres.
|
|
7-02 |
Project Manager Dan Baskins and Betsy
Peabody (PSRF) once again traveled to
Olympia
to lobby legislators
including House Speaker Frank Chopp on
behalf of the Pit to Pier Project.
|
|
10-22-02 |
After significant public and environmental
opposition to the 6,240 MRLO, FHM
submitted
a new request for
a 765 acre MRLO.
|
|
11-13-02 |
The Jefferson County Planning Commission
ultimately recommended a 690 acre MRLO
with Pit to Pier conditions
while at the same time denying any
relationship between the MRLO
and the Pit
to Pier Project.
|
|
12-9-02 |
The Jefferson County BOCC approved the 690
acre MRLO with Pit to Pier conditions
attached
while maintaining
there was no relationship between the MRLO
and the Pit to Pier Project.
|
|
2-21-03 |
The 690 MRLO granted by the BOCC was
appealed by the Hood Canal Coalition and
six other
equally concerned
organizations.
|
|
3-27-03 |
FHM submitted applications for both an
expanded mine and the Pit to Pier
Project. (Ultimate
approval will require
a “Conditional Use Permit” by Jefferson
County to allow FHM to use rural
residential designated property as the
platform for a massive
1000 foot long industrial pier.)
|
|
6-24-03 |
The MRLO appeal was heard before the
Western Washington Growth Management
Hearing
Board. |
|
8-15-03 |
The Hearing Board issued a ruling that
Jefferson County was not in compliance
with the State
Environmental
Protection Act (SEPA) in that they failed
to perform adequate environmental
assessments
|
|
8-22-03 |
Jefferson County filed a motion with the
WWGMHB asking for reconsideration of their
original
findings. |
|
8-25-03 |
FHM joined with Jefferson County in a
similar motion |
|
9-2-03 |
Hood Canal Coalition attorneys filed an
objection to these motions. |
|
9-11-03 |
The WWGMHB unanimously denied the FHM and
Jeff Co motions for reconsideration. |
|
1-22-04 |
Congressman Norm Dicks publicly stated his
opposition to the FHM Pit to Pier Project |
|
2-19-04 |
The Hearing Board moved the Compliance
Hearing from April to August providing
Jefferson
County additional time to prepare their case in the matter
of HCC et al versus Jefferson
County and FHM relating to the successful
HCC appeal of the County’s decision to
grant a
690 acre mining district to FHM.
|
|
5-25-04 |
An overflow crowd appeared at a BOCC
public hearing held at the Jeff Co
Courthouse. The
BOCC informed those
present that the public would not be
allowed to speak (FHM’s position).
The
meeting was cancelled because of
the large crowd and rescheduled for
6-7-04.
|
|
6-7-04 |
The rescheduled public hearing conducted
in order to comply with previous WWGMHB
direction was held at
Chimicum H.S. The BOCC reversed their
previous position and allowed
public
testimony.
|
|
6-30-04 |
The Jefferson County Commissioners despite
overwhelming opposition and testimony
approved the 690 acre
MRLO for the second time.
|
|
9-2-04 |
The WWGMHB Compliance Hearing was held to
determine whether or not Jefferson County
had rectified issues
identified in the board’s previous ruling
against the county.
|
|
9-15-04 |
FHM applied to Jefferson County DCD for a
10 acre expansion at the Shine Pit |
|
10-14-04 |
The WWGMHB ruled that Jefferson County was
now in compliance with SEPA and other
requirements regarding
their granting of the 690 acre MRLO to FHM.
|
|
11-15-04 |
The WWGMHB denied HCC’s request for
reconsideration of their 10-14-04 ruling
in favor of
Jefferson County. |
|
11-19-04 |
Jefferson County DCD granted the 10 acre
expansion at the Shine Pit issuing a
determination
of non-significance
(no environmental impact).
|
|
11-04 |
Two of the Jefferson County Commissioners
(Titterness and Huntingford) who had on
two
occasions approved
the 690 acre MRLO were not re-elected to
office.
|
|
12-15-04 |
HCC and 6 other organizations filed a
Petition for Judicial Review in Jefferson
County Superior
Court of the
WWGMHB’s denial of reconsideration of
their 10-14-04 ruling. (This court appeal
is still pending)
|
|
12-04 |
FHM requested that DCD proceed with
processing their 7-3-03 application for a
156 acre mine
in the Wahl Lake
area of the 690 acre MRLO. DCD allowed
public input and extended the
comment
period several times.
|
|
1-26-05 |
Jefferson County DCD released an RFQ for
the EIS on the FHM Pit to Pier proposal. |
|
3-30-05 |
Jefferson County DCD issued a Mitigated
Determination of Non Significance (MDNS)
for the
156 acre Wahl Lake
strip mining request finding that it posed
no environmental threat and did
not
require an EIS or public comment.
|
|
4-4-05 |
FHM attorney Jim Tracy appeared at a
Jefferson County BOCC meeting and
incorrectly
admonished the newly
elected commissioners that they were
prohibited from hearing or
receiving
public comment on the Wahl Lake
permit or the Pit to Pier proposal.
|
|
4-13-05 |
Based upon the volume of protests from
environmental groups, the tribes, WDFW,
independent consultants, HCC
and the public DCD extended the comment
period regarding
their MDNS finding on the
Wahl Lake 156 acre strip
mine until 4-20-05.
|
|
5-12-05 |
Based upon overwhelming public comment and
scientific data DCD withdrew their MDNS
finding on the 156 acre
Wahl Lake extraction area. They changed
their finding to a
Determination of
Significance (DS) and required a
full EIS.
|
|
6-22-05 |
After pressure from FHM and submission of
a revised application by the company, DCD
flip
flopped once again
and re-issued a MDNS for the 156 acre Wahl
Lake strip mine.
|
|
7-18-05 |
Jefferson County DCD again reversed
themselves. Although proceeding with a
MDNS finding
DCD restricted the
SEPA determination to only 39 acres of the
156 acres originally requested.
This
permit is critical as it is a major
step forward in FHM’s attempt to piecemeal
the Pit to
Pier project.
|
|
10-05 |
Formal evaluation and a full EIS are still
pending on the Pit to Pier application
filed by FHM in
March, 2003. There has been little activity on the Pit
to Pier specific applications since DCD
issued the RFQ for the EIS in
January, 2005. However FHM continues to
pursue the Wahl
Lake mine and has
constructed a 1 ¼ mile cement
road bed for the conveyor belt from the
Wahl Lake site to the Shine Pit. Jefferson
County DCD did not require any
permits for this
considerable construction
project.
|