HOOD CANAL COALITION |
|
|---|---|
NEWS ARTICLES OF INTEREST GENDLER & MANN, LLP attorney s-at-law Michael W.Gendler
(206)621-8868 VIA FACSIMILE TO (360)379-4451 Al Scalf, Director RE: MDNS dated June 22, 2005 on Fred Hill Materials revised application for Wahl Extraction Area Dear Mr. Scalf: This letter and the letter dated
July 6, 2005 from Peter Schwartzman of Pacific
Groundwater Group are submitted on behalf of the Hood Canal Coalition in response to
Jefferson County's issuance of a
Mitigated Determination of Nonsignificance (MDNS)
for Fred Hill Materials' (FHM) revised application for a stormwater permit for surface mining in
the Wahl Extraction Area. The revised proposal is
essentially the same proposal for which
Jefferson County stated its intent to issue a Determination of
Significance (DS) on May 12, 2005. The only
changes are the "resequencing" of the areas to
be mined within the 165-acre Wahl Extraction
Area, and the proposal to develop a monitoring
plan specific to "Group One," the 38-acre
segment which would be mined first under the
revised proposal. One area will not itself have significant adverse impacts. For these reasons, the County should withdraw the new MDNS and issue a DS in accordance with the May 12, 2005 memorandum. The concept of "phased review" under SEPA does not support this MDNS. The greatest problem here is that the MDNS purports to cover the entire 165-acre Wahl area. Assuming for the moment that an MDNS is justified for the 38-acre "Group One" area, there is no justification for such an MDNS to include areas beyond Group One. Indeed, this is contrary to the SEPA rule on phasing, to "exclude from consideration issues . . . not yet ready." WAC 197-ll-060(5)(b). This is all the more so where the only permit now sought is the stormwater permit for the 38-acre Group One area. The County should not make its SEPA determination in advance of future permit applications. 2. The Resequencing Does Not Avoid Significant Adverse Impact The County correctly determined that FHM's proposal to mine 137 acres in its 165-acre Wahl area would have probable significant adverse impacts and therefore required a DS. FHM's subsequent revision to resequence the mining does not change that conclusion. Accordingly, the DS should have been retained. FHM still proposes to mine fully the same 137 acres it originally had proposed. The only difference is that it now intends to begin the work in another part of the area. But FHM has not offered data or evidence on which to conclude that the "resequencing" will avoid significant impacts. As the Pacific Groundwater Group comment points out, there is not a basis to conclude that mining one area within the Thorndyke Creek watershed will affect base flows significantly less than mining another area. Letter at 2 & n. 1. That the Group One area is further away from the creek than other areas now sequenced to be mined later might affect impacts from phenomena such as erosion, but there is no bassi to conclude that it will significantly change the impact with respect to groundwater resources. As Pacific Groundwater Group
points out, mining in the Group One area can be
expected to have about 25% of the cumulative adverse impact of mining the entire 137
acres. Their letter references their
prior estimate of a 3% impact to Thorndyke Creek
baseflow, such that the current
proposal's impact might be estimated at 0.8%.
But it must be emphasized (as the Pacific
Groundwater Group letter has done) that the 3%
estimate was made without the benefit of data
that the applicant has chosen not to supply,
regarding the site-specific soil texture. The
Pacific Groundwater
Group estimate of impact was accompanied by an
explanation of the uncertainties inherent
in such a preliminary estimate. It must be kept
in mind that there is considerable uncertainty,
which will remain unless the proposed monitoring
provides conclusive results or modeling analysis is conducted. Al Scalf Given this uncertainty, and a preliminary estimate of impact of 0.8% to baseflows associated with Group One mining alone, the Department of Ecology's actions to protect Water Resource Inventory Area 17 in Jefferson County provide a useful perspective. The Department of Ecology has determined that new water withdrawals should not be allowed in watersheds it considers to be in critical condition if the withdrawals would result in an impact of 1% to base flows or greater. It is our understanding that the Washington Department of Fish and Wildlife concurs in Ecology's determination. The Pacific Groundwater Group's preliminary estimate of impact of mining Group One alone at 0.8% is nearly the equivalent of Ecology's 1% figure used to decide whether to approve new groundwater withdrawal applications, especially given the uncertainties and potential for greater impact here. Accordingly, the County should not assume or conclude that the impacts of mining Group One alone will not be significant. Moreover, such a conclusion would be contrary to the SEPA rule that environmental review should not be fragmented to "avoid discussion of cumulative impacts" or to "segment and avoid present consideration of proposals and their impacts." WAC 197-ll-060(5)(d)(ii), (iii). Thus, even if the County proceeded on the basis that the impacts of Group One mining alone did not appear significant, it still would be improper to proceed with an MDNS because that would avoid consideration of the cumulative impacts through segmentation, contrary to the cited SEPA rules. As Pacific Groundwater Group has pointed out, the County has not developed a quantitative threshold for significant impacts to groundwater. This is all the more reason why the DS should be retained in a situation where the question of the significance of impacts from the first mining segment alone might be viewed as a "close call." We assume that one justification
for the MDNS is the premise that segmenting the
mining into a first 38-acre group enables the County to obtain
monitoring data before commitments are made to approve additional mining. While this may
have some appeal, it is wrong for three reasons. First, as Pacific Groundwater
Group has pointed out, the County has not yet
developed quantitative criteria to determine whether the
impacts will be significant. Absent such
criteria, it may well be
that the first segment alone will have
significant adverse impacts which would only be discovered after the fact. This is because the monitoring data will
not be evaluated until after the first
group is mined and because FHM has not yet
provided a defensible site-specific hydrologic evaluation of how excavation would change the timing of
recharge and therefore base flows in
Thorndyke Creek. Second, also as explained in
the Pacific Groundwater Group comment, it
is doubtful whether the monitoring data to be
developed as the first segment is mined will provide a sufficient basis to determine whether impacts
associated with additional segments are
significant. This point will be addressed in the
next section of this comment letter. Third, the
County's MDNS does not limit its scope to the
current 38-acre proposal for which a stormwater
permit is sought. Instead, the MDNS states that
it applies to the entire 165-acre area. While
the County has identified potential escape
routes from the consequences of this premature and
overinclusive SEPA determination, even with
these future reviews it is wrong to issue an MDNS for mining for which a permit is not yet being
requested. The section after next of this Al Scalf 3. Monitoring Data Cannot Be Expected to Ensure That the Impacts of Additional Mining Will Not Be Significant The premise that the resequencing of the
revised proposal will enable the applicant and
County to gather enough monitoring data so that
significant adverse impacts can be avoided with
future mining segments is not substantiated.
There may be good intention behind the notion of
developing this data, and the Hood Canal
Coalition supports the monitoring requirements
as part of any approval issued after proper
environmental review pursuant to a DS. But these
good intentions do not substitute for good data
and good reason to conclude (rather than just
believe) that the monitoring will make a real
difference in the ability to determine the
impacts. As Pacific Groundwater Group has
explained, the data "noise" resulting from
rainfall variation and other climactic factors
is very likely to drown out the changes in
stream flows attributable to mining. But this
certainly does not mean that the impacts to
stream flows attributable to mining are not
significant. Instead, it means that such impacts
are difficult to isolate and evaluate through
the type of monitoring the applicant has
proposed. Accordingly, the County does not have
a basis to conclude that an EIS is not necessary
on the basis that data and analyses will be
developed in time, before any significant
adverse impacts occur.It must be kept in mind that the purpose of
an EIS is to evaluate the probable adverse
impacts of a proposal. A requirement for a
future study does not prevent impacts or
mitigate impacts. Instead, it postpones the
environmental review which the County has
recognized in this very case is required for the
overall project, while allowing the first
segment to proceed without that required review.
Again, this is contrary to the SEPA rule against
review which "would segment and avoid present
consideration of proposals and their impacts."
WAC 197-ll-060(5)(d)(iii). The better course,
and indeed the one recognized by the County on
May 12, 2005, is to require an EIS for the
entire Wahl area so that impacts can be
evaluated before any of them occur and so that
the benefit of analyses which could identify
measures to avoid impacts can be obtained and
applied to the entire mining sequence, not just
its later segments. 4. The County Should Not Segment Review and "Phased Review" Does Not Justify the MDNS The SEPA rules prohibit "segmenting" a
project to avoid consideration of its cumulative
effects before the project begins. WAC
197-ll-060(5)(d). Notwithstanding this, "phased
review" is allowed under SEPA. It must be noted,
however, that phased review here does not fit
into the situations identified in the SEPA rules
as most appropriate for such review. The two
general situations where phased review is
appropriate are identified in WAC 197-1
l-060(5)(c). But this is not a situation where
the sequence is from a nonproject document to a
site-specific analysis, nor is it one where the
sequence is from an early stage on a specific
proposal such as site selection to a later one
such as sensitive design impacts. WAC 197-1
l-060(5)(c)(i), (ii).More important, the circumstances here are
within the examples in WAC 197-ll-060(5)(d)
where phased review is not appropriate. The rule
specifies that "phased review is not appropriate
when ... it would merely divide a larger system
into exempted fragments or avoid discussion of
cumulative impacts." WAC 197-ll-060(5)(d)(ii).
The issuance of an MDNS for the entire 165-acre
area violates that rule because it "avoids
discussion of cumulative impacts" of mining the
entire area. There is no doubt that the
groundwater impacts will be "cumulative."
Notwithstanding the good intention of monitoring
through the first project segment, phased review
here runs afoul of this rule.This also violates the next subsection, that
"phased review is not appropriate when it would
segment and avoid present consideration of
proposals and their impacts." WAC 197-11-060(5)(d)(iii).
The result of the MDNS is to "avoid present consideration of the impacts associated with
mining FHM's Wahl unit. This is the SEPA rule
that embodies the well-known concept of project
"segmentation," i.e., dividing a project into
"segments" to avoid full environmental review
because the impacts associated with each
"segment" appear to be less than significant. It
is noteworthy that both the applicant and the
County use the term "segments" to describe the
resequenced mining areas. Especially where the
impacts associated with the first project
segment alone likely are comparable to
groundwater impacts deemed "significant" and
unacceptable by the state agency charged with
protecting groundwater, and where the data
developed through monitoring of that first
project segment will not likely prove sufficient
to prevent further cumulative impacts, this is a
classic situation of "segmentation" which is
contrary to the SEPA rules.There is another important reason why this
MDNS cannot be sustained as "phased review."
"Phased review" requires that there be a future
environmental review under SEPA, i.e., the
second "phase." Here, an MDNS has been issued
for the entire 165-acre area, such that there
will not be the future phase that is
necessarily part and parcel of "phased review."
Whether or not phased review would be
supportable even though this application does
not fit within the 5. Other Comments The June 22, 2005 MDNS mentions the June 1, 2005 on-site meeting, but does not mention that anadromous fish were observed in the unnamed tributary to Thorndyke Creek. This certainly was an important observation, and it was contrary to the assertions of the applicant that there were not fish made to justify not having to prepare an EIS.We reference and incorporate our prior comments regarding this proposal, hi particular, we have called attention to Finding 37 in Ordinance 8 (approved one year ago today), in which the Board of County Commissioners specified that the marine transportation alternative would have to be studied in conjunction with any mining proposal within the MRLO. We renew our call to the County to acknowledge and honor that directive. 6. Conclusion The Hood Canal Coalition appreciates the
opportunity to submit this comment with regard
to the June 22, 2005 MDNS. For the reasons
stated, an MDNS for future mining proposals that
Very truly yours, MWG:den cc: Hood Canal Coalition
|
|
| ©2002-2010 HOOD CANAL COALITION P.O.Box 65279 | Port Ludlow, WA | 98365 |
|